Eco2 – committed to the future of renewable energy

Mains of Hatton Wind Farm

The Mains of Hatton Wind Farm, located in Aberdeenshire, received full planning permission in January 2010.

Eco2 and joint venture partners AJ Duncan successfully sold the development to Merepark Eco2 Wind EIS Ltd in October 2011.

After successfully completing the construction phase, Eco2 is currently managing the operation of the wind farm on behalf of the new owners.

Site Statistics
Turbine tower height 55m
Turbine blade length 24m
Number of turbines 3
Single Turbine Capacity 800kW
Maximum Wind Farm capacity 2.4MW
Operational Period 25 years
Predicted annual output Approximately 6,800MWh
Electricity equivalent Approximately 1,375 households
Project Benefits
Environmental Benefits
  • The project will make a significant contribution to the reduction of emissions that are known to cause global warming and acid rain. Over the 25-year lifetime of the project, it will displace approximately 67,000 tonnes of CO2.*

* The range of CO2 saving is calculated due to the portfolio mix of UK energy supply